CP2 – Marine Facilities

Scope

Comprises onshore mineral products receival, a minerals storage shed and load out facilities, a conveyor system, wharf and ship loaders with an interconnecting jetty.

Construction Milestones
Jul 2012 – Earthworks Started
Sep 2012 – Storage Shed Foundations Started
Oct 2012 – Marine Works Started
Jul 2013 – Storage Shed Completed
Aug 2013 – Marine Works Completed
Oct 2013 – Ship Loader Installed
Feb 2014 – First Shipment of Minerals