CP3 – Power Line and Substation

Scope
The package comprises a 14km 132kV power transmission line connecting the Galu Substation to the mine site and a terminating substation and distribution system on site.

Construction Milestones
Aug 2012 – Wayleave Cleared
Sep 2012 – Tower Foundations Cast
Sep 2012 – Towers Erected
Oct 2012 – Overhead Line Completed
Mar 2013 – Substation Installed
Apr 2013 – Line Energised

Your email address will not be published. Required fields are marked *