Scope
8km sealed road linking the mine site to the A14 coastal highway and widening of the highway at the junction.
Construction Milestones
Nov 2011 – Clearing Started
Dec 2011 – Layer Works Started
Apr 2012 – Culverts Completed
Sep 2012 – Base Stabilisation Completed
Sep 2012 – Prime Coating Installed
Oct 2012 – Asphalting Started
May 2013 – Road Completed