WP1 – Owner’s Projects

Scope

The scope comprises procurement of the mobile mining fleet and the dozer trap mining unit, construction of the borefield as a supplementary source of water supply, topsoil stripping, process plants commissioning spares and first fills.

Construction Milestones
Nov 2011 – Mobile Mining Equipment Ordered
Jul 2012 – Borehole Drilling Started
Apr 2013 – Mobile Mining Equipment Delivered
Jun 2013 – Borefield Pipeline Installed
Jun 2013 – Mine Pre-stripping Completed
Aug 2013 – Dozer Trap Mining Unit Installed
Sep 2013 – Borefield Completed