CP4 – Mukurumudzi Dam

Scope
This package comprises an 8.8 million cubic metres water storage dam on the Mukurumudzi River with associated spillway. The earth embankment is 22 metres high with a span of 350 metres.

Construction Milestones
Jan 2012 – Site Clearing Started
Mar 2012 – Diversion Culvert Downstream Section Completed
Sep 2012 – Longitudinal Coffer & Embankment Foundations Completed
Oct 2012 – Diversion Culvert Completed
Nov 2012 – River Diverted Through Culvert
Apr 2013 – Culvert Closed & Installation of Outlet Works Started
Jul 2013 – Embankment Construction Completed
Aug 2013 – Spillway Completion